CategoryAreaADOLFO CAMARILLO HIGH SCHOOLStatusCompleted
Site Safety & SecurityFencing and BarriersSecurity ImprovementsKBZ bid documents under DSA review
Site Safety & SecurityLighting and CommunicationsLighting in QuadCompleted 2019
Site Safety & SecurityLighting and CommunicationsPA System/Intercom Outside SpeakersIMEG preparing bid documents
Site Safety & SecurityAsphalt PavingParking Lot Pick-up Drop-off, Flow & SafetyCompleted 2018
Site Safety & SecurityFencing and BarriersRenovate Admin. Building EntryG2K Cons under contract
FieldsDrainage and WasteSite Drainage ImprovementsLittle documents DSA approved
FieldsFields and TurfRenovate Fields & Artificial Turf at StadiumOHNO Cons under contract
FieldsDrainage and WastePlumbing-Replace Field Septic SystemLater Phase
FieldsFields and TurfStadium Lighting ReplacementLittle preparing bid documents
FieldsFields and TurfSnack Shack-New BuildingLater Phase
HVACBuilding AirHVAC-New ThroughoutF&M bid documents under DSA review
HVACBuilding AirRoofing ReplacementCompleted 2018
HVACSite ElectricalElectrical InfrastructureF&M bid documents under DSA review
HVACBuilding AirNew Window CoveringsF&M bid documents under DSA review
Classroom Window Replacement AddedF&M bid documents under DSA review
Classroom LED Lighting AddedF&M bid documents under DSA review
ModernizationActivity and PerformanceLittle Theater RenovationLater Phase
ModernizationActivity and PerformanceGym ModernizationDCA preparing bid documents
ModernizationClassroom Support AreasCafeteria Storage AdditionLater Phase
ModernizationActivity and PerformanceMusic Building AcousticsLater Phase
ModernizationClassroom Support AreasReplace Finishes at LibraryLater Phase
ModernizationClassroom Support AreasRelocate IT OfficeCompleted 2018
ModernizationActivity and PerformanceI Wing-Renovate Activity RoomLater Phase
RelocatablesClassroom ReplacmentReplace Portable Classrooms-AG, T3 & T4 wingsF&M bid documents under DSA review
Leased Relocatables AddedDCA preparing bid documents
Career Ed. Tech.Career Ed. TechAg. Building Addition (potential CTE grant)F&M assisting with funding application
Career Ed. Tech.Career Ed. TechI-Wing-Renovate Woodshop into Maker SpaceF&M assisting with funding application
PACPerforming Arts CenterSmall PACLater Phase
CategoryAreaCHANNEL ISLANDS HIGH SCHOOLStatusCompleted
Site Safety & SecurityFencing and BarriersSecurity ImprovementsKBZ bid documents under DSA review
Site Safety & SecurityFencing and BarriersConex Boxes RelocationCompleted 2019
Site Safety & SecurityFencing and BarriersClassroom Door Lock-Blok RetrofitCompleted 2018
Site Safety & SecurityFencing and BarriersAdministration Building Entry RenovationG2K Cons under contract
Site Safety & SecurityFencing and BarriersMaintenance Building SecurityCompleted 2018
Site Safety & SecurityLighting and CommunicationsLighting in QuadCompleted 2019
Site Safety & SecurityAsphalt PavingReplace Asphalt Paving in Parking LotsCompleted 2018
FieldsDrainage and WasteSite Drainage ImprovementsLittle bid documents under DSA review
FieldsFields and TurfRenovate Fields & New Artificial Turf at StadiumLittle bid documents under DSA review
FieldsFields and TurfField Restrooms & Snack Bar RenovationLittle bid documents under DSA review
FieldsFields and TurfTennis Court ReplacmentLittle bid documents under DSA review
FieldsFields and TurfField Entrance & Ticket Booth ImprovementsLittle bid documents under DSA review
HVACBuilding AirUpgrade Fire Alarm SystemF&M preparing bid documents
HVACBuilding AirRoofing Repair at ClassroomsCompleted 2018
HVACSite ElectricalElectrical Infrastructure UpgradesF&M preparing bid documents
HVACBuilding AirNew Window CoveringsF&M preparing bid documents
HVACBuilding AirReplace Locker Room WindowsF&M preparing bid documents
HVACBuilding AirHVAC-New ThroughoutF&M preparing bid documents
Classroom Window Replacement AddedF&M preparing bid documents
Classroom LED Lighting AddedF&M preparing bid documents
ModernizationClassroom Support AreasElevator Tower RepairCompleted 2018
ModernizationActivity and PerformanceGym ModernizationDCA preparing bid documents
ModernizationClassroom Support AreasComputer Lab Exiting RenovationsLater Phase
ModernizationClassroom RenovationRepairs at 2-story ClassroomsLater Phase
ModernizationClassroom Support AreasCafeteria and Lunch Shelter RenovationLater Phase
ModernizationClassroom RenovationMisc. Repairs in N and T wingsLater Phase
RelocateablesClassroom ReplacmentReplace Portable Classrooms-M wingF&M bid documents under DSA review
Leased Relocateables AddedDCA preparing bid documents
Career Ed. Tech.Career Ed. TechRenovate Woodshop into Maker SpaceF&M preparing bid documents
PoolPoolNew Pool and Aquatics CenterA4E preparing design RFP
PACPerforming Arts CenterSmall PACLater Phase
CategoryAreaFRONTIER HIGH SCHOOLStatusCompleted
Site Safety & SecurityAsphalt PavingParking Lot Path of TravelCompleted 2018
Site Safety & SecurityFencing & BarriersMiscellaneous Site ImprovementsKBZ bid documents under DSA review
Site Safety & SecurityFencing & BarriersSecurity ImprovementsCompleted 2019
ModernizationClassroom RenovationReplace Roofing & GuttersProFab Cons proposal pending
ModernizationClassroom Support AreasLunch Room Code Compliance RenovationHMC to provide master plan proposal
ModernizationActivity and PerformanceWeight Room Floor RetrofitHMC to provide master plan proposal
ModernizationClassroom Support AreasAdministration Building ModernizationHMC to provide master plan proposal
ModernizationClassroom RenovationModernization-Classrooms #12-#20HMC to provide master plan proposal
RelocateablesClassroom ReplacementNew Restroom BuildingHMC to provide master plan proposal
RelocateablesClassroom ReplacementNew Library BuildingHMC to provide master plan proposal
MPRMulti-Purpose BuildingNew Multi-Purpose BuildingHMC to provide master plan proposa
Shade StructureShade StructureNew lunch shelterHMC to provide master plan proposal
CategoryAreaHUENEME HIGH SCHOOLStatusCompleted
Site Safety & SecurityFencing and BarriersSecurity ImprovementsKBZ bid documents under DSA review
Site Safety & SecurityFencing and BarriersSite Fencing ReplacementKBZ bid documents under DSA review
Site Safety & SecurityFencing and BarriersConex Boxes RelocationCompleted 2019
Site Safety & SecurityFencing and BarriersAdministration Building Entry RenovationG2K Cons under contract
Site Safety & SecurityFencing and BarriersClassroom Door Lock-Block RetrofitCompleted 2018
Site Safety & SecurityFencing and BarriersMaintenance Building SecurityCompleted 2018
Site Safety & SecurityAsphalt PavingReplace Asphalt Paving in Parking LotsCompleted 2018
FieldsFields and TurfRenovate Fields & New Artificial Turf at StadiumLittle bid documents under DSA review
FieldsFields and TurfTennis Court ReplacmentLittle bid documents under DSA review
FieldsFields and TurfField Entrance and Ticket Booth ImprovmentsLittle bid documents under DSA review
HVACSite ElectricalElectrical-Replace Equipment at D wingLater Phase
HVACSite ElectricalElectrical Infrastructure UpgradesF&M preparing bid documents
HVACBuilding AirNew Window CoveringsF&M preparing bid documents
HVACBuilding AirHVAC-New ThroughoutF&M preparing bid documents
Classroom Window Replacement AddedF&M preparing bid documents
Classroom LED Lighting AddedF&M preparing bid documents
ModernizationActivity and PerformanceGym ModernizationDCA prepaing bid documents
ModernizationClassroom Support AreasCafeteria Kitchen RenovationLater Phase
ModernizationActivity and PerformanceLocker Rooms Ventilation and Misc. RepairsF&M preparing bid documents
ModernizationClassrooom RenovationH Wing RenovationLater Phase
ModernizationActivity and PerformanceReplace Finishes in Music BuildingLater Phase
ModernizationClassrooom RenovationMisc. Repairs in Q and R wingsLater Phase
RelocateablesClassroom ReplacmentReplace Portable Classrooms-O, Q, and U5 wingsF&M bid documents under DSA review
DCA preparing bid documents
Career Ed. Tech.Career Ed. TechRenovate Old Shops into Maker Space-H wingF&M assisting with funding application
Career Ed. Tech.Career Ed. TechRenovate Old Home Ec. Classrooms into Culinary Arts ProgramF&M assisting with funding application
PACPerforming Arts CenterSmall PACLater Phase
CategoryAreaOXNARD HIGH SCHOOLStatusCompleted
Site Safety & SecurityFencing and BarriersSecurity ImprovementsKBZ bid documents under DSA review
Site Safety & SecurityAsphalt PavingParking Lot Pick-up, Drop-off, Flow & SafetyCompleted 2018
FieldsFields and TurfArtificial Turf Field at StadiumLittle bid documents under review
HVACBuilding HVACHVAC-New ThroughoutWLC preparing bid documents
ModernizationClassroom RenovationModernization Throughout CampusLater Phase
RelocateablesClassroom ReplacementReplace Portable ClassroomsLater Phase
PoolPoolPool Deck Replacement & UpgradesArdalan Cons under contract
ShelterShade StructureNew Lunch Shelter(s)Later Phase
CategoryAreaPACIFICA HIGH SCHOOLStatusCompleted
Site Safety & SecurityFencing & BarriersSecurity Improvements & Entry Security AdditionKBZ bid documents under DSA review
Site Safety & SecurityLighting and CommunicationsLighting in QuadCompleted 2019
Site Safety & SecurityAsphalt PavingParking Lot Pick-up, Drop-off, Flow & SafetyCompleted 2018
Site Safety & SecurityFencing & BarriersConex Boxes RelocationCompleted 2019
Site Safety & SecurityFencing & BarriersMaintenance Building SecurityCompleted 2018
FieldsFields ad TurfRenovate Fields & New Artificial Turf Field at StadiumOHNO Cons under contract
FieldsFields ad TurfLandscape ReplacementLater Phase
HVACBuilding HVACRoofing and Skylights RepairCompleted 2018
HVACBuilding HVACRepair Windows and Replace CoveringsLater Phase
HVACBuilding HVACHVAC-New ThroughoutWLC preparing bid documents
ModernizationActivity and PerformanceGym RepairSFG Cons under contract
ModernizationActivity and PerformanceGym Roof AccessLater Phase
ModernizationClassroom Support AreasAdministration Building RepairsLater Phase
ModernizationClassroom RenovationCarpeting-Replace Throughout with VCTLater Phase
ModernizationClassroom RenovationWall Coverings-Replace Throughout Classroom BuildingsLater Phase
ModernizationActivity and PerformanceMulti-Purpose Room Minor ModificationsLater Phase
ModernizationClassroom Support AreasFaculty Dining RenovationLater Phase
ModernizationActivity and PerformancePerforming Arts Center RepairsLater Phase
PoolPoolNew Pool and Aquatic CenterA4E preparing design RFP
CategoryAreaRANCHO CAMPANA HIGH SCHOOLStatusCompleted
HVACBuilding HVACHVAC-New ThroughoutF&M bid documents under DSA review
HVACBuilding HVACSkylight Shades in ClassroomsF&M bid documents under DSA review
Relocateables9 RelocateablesF&M bid documents DSA approved
RenovationClassroom Support AreasMaintenance Building Office and Restroom ImprovementsLater Phase
RenovationClassroom Support AreasStorage BuildingLater Phase
RenovationActivity and PerformanceLocker Room AdditionLater Phase
CategoryAreaRIO MESA HIGH SCHOOLStatusCompleted
Site Safety & SecurityFencing and BarriersSecurity ImprovementsKBZ bid documents under DSA review
Site Safety & SecurityAsphalt PavingParking Lot Pick-up, Drop-of, Flow & SafetyCompleted 2018
FieldsFields and TurfRenovate Field Restrooms and Snack BarLittle bid documents under DSA review
FieldsFields and TurfLandscape Renovation at Front of SchoolLater Phase
FieldsFields and TurfArtificial Turf Field at StadiumLittle bid documents under DSA review
FieldsDrainage and WasteSite Drainage ImprovementsLittle bid documents under DSA review
HVACSite ElectricalElectrical Infrastructure UpgradesF&M preparing bid documents
HVACBuilding HVACNew Window CoveringsF&M preparing bid documents
HVACBuilding HVACHVAC-New ThroughoutF&M preparing bid documents
Classroom Window Replacement AddedF&M preparing bid documents
Classroom LED Lighting AddedF&M preparing bid documents
ModernizationActivity and PerformancePhase 1 Modernization-GymDCA preparing bid documents
ModernizationClassroom Support AreasCafeteria Kitchen Miscellaneous RenovationsLater Phase
ModernizationClassroom RenovationModernization-D, L, M, N, R, and U wingsLater Phase
ModernizationActivity and PerformanceStadium ModernizationLittle preparing bid documents
ModernizationClassroom RenovationSpecial Ed Classroom RenovationsLater Phase
ModernizationClassroom RenovationMisc. Repairs in A and K WingsLater Phase
RelocateablesClassroom ReplacementReplace Relocateables Classrooms except R wing officesF&M bid documents under DSA review
RelocateablesClassroom ReplacementNew RestroomsF&M bid documents under DSA review
Career Ed. Tech.Carreer Ed. TechMERIT Program H wing RenovationF&M assisting with funding application
Career Ed. Tech.Carreer Ed. TechAuto Shop Addition and RenovationF&M assisting with funding application
PACPerforming Arts CenterSmall PACLater Phase